The Apps Team is currently working on the following:

  • CIM - lead engineer, Weidner
    • v8.1 release - target date 7/31.  Currently 70 bugs in progress
      • Code Freeze moved from 7/18 -> 7/25 due to scheduled vacations
      • 7/28: RC Build - This build will be available on a limited bases (restricted customer list).
      • DB Assessment: In process. Driving to get key data by 7/25
      • Load Testing: Tentatively scheduled for mid-August. Load Test Plan in progress.
      • End Game: 9 bugs remaining (Triage Approved) for final RC. ETA: 8/5
      • RBC Build: 7/31 - Required drop to RBC (Build 418 assumed)
      • Dev Doc Review in process.
    • Connextions Cobrowse Patch: Completed 7/15
    • JAWS / BMO Server Delivered: 7/15
    • 8.1 Early Bits for RBC: Delivered 7/15
    • v8.0.3 hotfix 2 release
      • Due: 7/18
      • Completed: 7/18
      • HF2 has been uploaded and is available for general use.
      • HF1 has been removed from the support site: Supplanted by HF2
    • ToDos:
      • Hit Glidepath for 8.1 Code Freeze
      • Schedule / Deliver 8.1 Training
      • Review / Deliver 8.1 Documentation.
      • Channels Transition Planning and Hiring
      • Channels 9.0 Feature Planning (with PM)
  • Knowledge Base - lead engineer, Hemal Kothari
    • Addressing customer issues with v8.0 upgrade
      • Customers have been restored back to v7.0.1 and are fully operational, and have their modified data back.
      • Patches have been developed for issues seen under load.
      • Working on a plan for simulating load on the 8.0.3 Shared Hosted platform (as seen on Live Platform).
      • Internal Load Testing using custom scripts & existing Tools.
      • External Load Testing - looking at 3rd parties (e.g. WebMetrics)
    • v8.1 release - target date - 7/31 (Original) - Currently: 80 Active Dev bugs.
      • Code Freeze: 7/25 - has been moved out because of Shared Hosted issues.
      • RC1 Build: Week of 7/28
      • Bug Stats:
    • Load Testing: Repeat same exercise (as v8.0.3) for 8.1.  Tentatively scheduled for August.
    • PM Communicated Date for Release of 8.1: Second half of August.
    • Todos:
      • Hit Glidepath for 8.1 and land the project.
      • Schedule training for Teams here (next week)
      • Waiting for draft of Documentation to review and provide feedback
      • Hiring (backfill for Dave's position).
      • Work-In-Progress - work with PM on KB 9.0 Feature planning
      • Work with team in Austin and collaborate on integration features for 9.0 and beyond.
  • nGen Collaboration (aka Hub) - lead engineer, Roeder
    • v7.0 (Jira feature list), contact mroeder@ngenera.com for access.
      • Highlights:
        • First pass at content service, using personal wiki as prototype
        • Twitter integration, user tweets + 'presence'
        • Converse/Reply by email
        • Facebook integration (profile merge at user service and pushed to hubs)
        • Templates (clone conv)
        • Search++
        • Wiki Versioning (?)
    • nGenera Hub support as needed
    • todos
      • Continue to ramp up new dev hires, John and Rodrigo, specifically towards 7.0
      • Work with Akif/platform team to hand over user service and platform build
  • nGen Compensation (aka TCS) - lead engineer, Gonzales
    • v2.0 GA Release - target date 7.17 (Final QA verification in progress)
    • v2.2 GA Release - target date 10.1
      • Feature Design - complete as of 7.11 (Feature List)
      • Development - start date 7.18
      • Testing - start date 9.8
    • Reporting and Datamart infrastructure 
      • Datamart enhancement to coinside with release 2.2
      • Additional features to be available in Q4 
    • enGine Performance improvements
    • Roadmap planning with SHeath and Shimberg. 
    • Widget exchange between nGen Comp and e.lab
      • Planned Release of 3 Widgets (wrapped JSR Portlets) for 2.2
        • Workflow - nGen Workflow
        • WhatIf - nGen Comp
        • Reports - Cognos
    • nGen Workflow discussion
  • Platform  - lead engineer, Schriftman
    • Developing Strategy Guide
    • Supporting SimOD Development
    • Hold. BSG RA communication and socializing - via the Architecture Review Team 
    • Hold. BSG RA documentation including:
      • BSG RA Patterns and Best Practices Guide
    • nGen Sales - a SFDC mashup - requires new content API. This will initially be implemented in the hub via a new controller (content_controller) and will partially migrated to the content service when it becomes available.
    • Counterparty integration - early stages - negotiate feature set with PM - will lead to the possible development of a complex relationship service, along with a set of relationship widgets
    • .NET Toolkit (starting with user service)
    • Storage Service (Shared document storage and file handling)
      • client: promotion of "document" to conversation model
      • client: plugin
      • server: clustering
  • Personnel and recruiting
    • Eng interviewing continues
      • JohnC, RodrigoD, AkimR, and JonathanB hired, starting 7/7, 7/7, 7/7, 7/21 
    • QA Director (MaartenM) hired, started 7/14
    • Revise personnel review forms
    • All-hands meeting 7/29
  • Quality Engineering (QE) - director, Metz 
    • Formalize Quality Engineering mission and intial Quality Priorities
    • Future.  Staffing plan, processes definitions
    • Week of 8/3:
      • Visit the NY office.
        • Get better understanding of products, processes and assets
        • Present my QE philosophy and methodology
      • Started initial conversations with Ukraine and Russian offshore companies, which will soon be followed by a more formal RFI process
  • Operations:
    • (Done) Configuration Jira for task management of nGen Collab and Platform.
    • Coordinate with David Krueger (and Bob Tapscott) on our datacenter strategy / migration
    • Create integration and staging environments with DavidK, MaartenM
    • (JimmyG) Upgrade Jira to head revision; install charting plugins
  • Research:
  • SimOD - currently on hold pending feedback and planning session with modeling team.  Anticipated future work and task list
  • Other business development activities
    • Baynote 
    • Queplix
    • SenseMaker 
    • Traverse
    • Zuora
  • (Ongoing) , especially as concerns Project Butterfly and Members Hub

The following projects are on hold (reason listed in parens):

  • (Need resources; waiting outcome of Traverse partnership) "YouTag" prototype
    • Phase 2: requirements collected from sourcing team (Berry, Bryan)
    • Several demos with Traverse Corporation concerning possible co-developing partnership
  • (Strategy unclear) nGen Talent roadmap w/ AndyS and ScottH
  • (Waiting on PM) nGen Customer roadmap planning with KellyL, FrankC, and RobB 
  • (Need resources) Ideastorm prototype