Attack Plan
Updated: July 14, 2008. Previous month's nGenera Apps Team Attack Plan - May 2008 Next month's nGenera Apps Team Attack Plan - August 2008
The Apps Team is currently working on the following:
- CIM - lead engineer, Weidner
- v8.1 release - target date 7/31. Currently 70 bugs in progress
- Code Freeze moved from 7/18 -> 7/25 due to scheduled vacations
- 7/28: RC Build - This build will be available on a limited bases (restricted customer list).
- DB Assessment: In process. Driving to get key data by 7/25
- Load Testing: Tentatively scheduled for mid-August. Load Test Plan in progress.
- End Game: 9 bugs remaining (Triage Approved) for final RC. ETA: 8/5
- RBC Build: 7/31 - Required drop to RBC (Build 418 assumed)
- Dev Doc Review in process.
- Connextions Cobrowse Patch: Completed 7/15
- JAWS / BMO Server Delivered: 7/15
- 8.1 Early Bits for RBC: Delivered 7/15
- v8.0.3 hotfix 2 release
- Due: 7/18
- Completed: 7/18
- HF2 has been uploaded and is available for general use.
- HF1 has been removed from the support site: Supplanted by HF2
- ToDos:
- Hit Glidepath for 8.1 Code Freeze
- Schedule / Deliver 8.1 Training
- Review / Deliver 8.1 Documentation.
- Channels Transition Planning and Hiring
- Channels 9.0 Feature Planning (with PM)
- v8.1 release - target date 7/31. Currently 70 bugs in progress
- Knowledge Base - lead engineer, Hemal Kothari
- Addressing customer issues with v8.0 upgrade
- Customers have been restored back to v7.0.1 and are fully operational, and have their modified data back.
- Patches have been developed for issues seen under load.
- Working on a plan for simulating load on the 8.0.3 Shared Hosted platform (as seen on Live Platform).
- Internal Load Testing using custom scripts & existing Tools.
- External Load Testing - looking at 3rd parties (e.g. WebMetrics)
- v8.1 release - target date - 7/31 (Original) - Currently: 80 Active Dev bugs.
- Code Freeze: 7/25 - has been moved out because of Shared Hosted issues.
- RC1 Build: Week of 7/28
- Bug Stats:
-
80 Bugs Assigned to Dev
- 9 A's
- 24 B's
- 21 C's
- 17 D's
- 9 E's -
Total Bugs for QA left to verify:
- 224 Resolved Bugs to resolve in next build 8.1.0.16 -
Link to VS Team Site: http://hqdevtfs.talisma.corp:8090/ (or http://207.77.61.35:8090), Project CIM 8.1. [don't know if this is reachable from outside?].
-
- Load Testing: Repeat same exercise (as v8.0.3) for 8.1. Tentatively scheduled for August.
- PM Communicated Date for Release of 8.1: Second half of August.
- Todos:
- Hit Glidepath for 8.1 and land the project.
- Schedule training for Teams here (next week)
- Waiting for draft of Documentation to review and provide feedback
- Hiring (backfill for Dave's position).
- Work-In-Progress - work with PM on KB 9.0 Feature planning
- Work with team in Austin and collaborate on integration features for 9.0 and beyond.
- Addressing customer issues with v8.0 upgrade
- nGen Collaboration (aka Hub) - lead engineer, Roeder
- v7.0 (Jira feature list), contact mroeder@ngenera.com for access.
- Highlights:
- First pass at content service, using personal wiki as prototype
- Twitter integration, user tweets + 'presence'
- Converse/Reply by email
- Facebook integration (profile merge at user service and pushed to hubs)
- Templates (clone conv)
- Search++
- Wiki Versioning (?)
- Highlights:
- nGenera Hub support as needed
- todos
- Continue to ramp up new dev hires, John and Rodrigo, specifically towards 7.0
- Work with Akif/platform team to hand over user service and platform build
- v7.0 (Jira feature list), contact mroeder@ngenera.com for access.
- nGen Compensation (aka TCS) - lead engineer, Gonzales
- v2.0 GA Release - target date 7.17 (Final QA verification in progress)
- v2.2 GA Release - target date 10.1
- Feature Design - complete as of 7.11 (Feature List)
- Development - start date 7.18
- Testing - start date 9.8
- Reporting and Datamart infrastructure
- Datamart enhancement to coinside with release 2.2
- Additional features to be available in Q4
- enGine Performance improvements
- Roadmap planning with SHeath and Shimberg.
- nGen Compensation product discussion group.
- Widget exchange between nGen Comp and e.lab
- Planned Release of 3 Widgets (wrapped JSR Portlets) for 2.2
- Workflow - nGen Workflow
- WhatIf - nGen Comp
- Reports - Cognos
- Planned Release of 3 Widgets (wrapped JSR Portlets) for 2.2
- nGen Workflow discussion
- Initial discussion - completed
- Conversations created
- Todo
- Evaluation Checklist (See Requirements wiki)
- Follow on meetings
- Platform - lead engineer, Schriftman
- Developing Strategy Guide
- Supporting SimOD Development
- Hold. BSG RA communication and socializing - via the Architecture Review Team
- Hold. BSG RA documentation including:
- BSG RA Patterns and Best Practices Guide
- nGen Sales - a SFDC mashup - requires new content API. This will initially be implemented in the hub via a new controller (content_controller) and will partially migrated to the content service when it becomes available.
- Counterparty integration - early stages - negotiate feature set with PM - will lead to the possible development of a complex relationship service, along with a set of relationship widgets
- .NET Toolkit (starting with user service)
- Storage Service (Shared document storage and file handling)
- client: promotion of "document" to conversation model
- client: plugin
- server: clustering
- Personnel and recruiting
- Eng interviewing continues
- JohnC, RodrigoD, AkimR, and JonathanB hired, starting 7/7, 7/7, 7/7, 7/21
- QA Director (MaartenM) hired, started 7/14
- Revise personnel review forms
- All-hands meeting 7/29
- Eng interviewing continues
- Quality Engineering (QE) - director, Metz
- Formalize Quality Engineering mission and intial Quality Priorities
- Future. Staffing plan, processes definitions
- Week of 8/3:
- Visit the NY office.
- Get better understanding of products, processes and assets
- Present my QE philosophy and methodology
- Started initial conversations with Ukraine and Russian offshore companies, which will soon be followed by a more formal RFI process
- Visit the NY office.
- Operations:
- (Done) Configuration Jira for task management of nGen Collab and Platform.
- Coordinate with David Krueger (and Bob Tapscott) on our datacenter strategy / migration
- Create integration and staging environments with DavidK, MaartenM
- (JimmyG) Upgrade Jira to head revision; install charting plugins
- Research:
- Widgetbox
- http://code.google.com/apis/gadgets/docs/spec.html
- Idea Storms (Bright Idea, etc)
- http://graphviz.com/
- http://www.dataportability.org/
- Google OpenSocial API: http://code.google.com/apis/opensocial
- Google Friend Connect
- Google App Engine: http://code.google.com/appengine/
- Summarization tool: http://www.alphaworks.ibm.com/tech/manyaspects/?open&ca=dna-flht-07242008&S_TACT=106AH62W&S_CMP=NEWS
- SimOD - currently on hold pending feedback and planning session with modeling team. Anticipated future work and task list
- Other business development activities
- Baynote
- Queplix
- SenseMaker
- Traverse
- Zuora
- (Ongoing) , especially as concerns Project Butterfly and Members Hub
The following projects are on hold (reason listed in parens):
- (Need resources; waiting outcome of Traverse partnership) "YouTag" prototype
- Phase 2: requirements collected from sourcing team (Berry, Bryan)
- Several demos with Traverse Corporation concerning possible co-developing partnership
- (Strategy unclear) nGen Talent roadmap w/ AndyS and ScottH
- (Waiting on PM) nGen Customer roadmap planning with KellyL, FrankC, and RobB
- (Need resources) Ideastorm prototype
Comments welcome.